House Fire
Arrival to estimate the damages
Cleaning Out the Debris
May 5th removal of debris begins.
Front View – Boarded Up & Cleaned Out
By May 5th the clean out is complete
Deconstruction
Removal of all burned parts of the structure
Rebuild Begins
By May 26th we have new walls completed
New Trusses & Roof
May 31st the trusses and new roof construction is underway.
Asbestos Contamination
Asbestos contamination identified and contained for remediation.
Rebuild Continues
Our crew completed the roof and new walls by the end of the day June 2nd.
Soda Blasting
June 7th, a before/after image of soda blasting any remaining wood burns from original timbers. This deodorizes while “sandblasting” simultaneously.
Vinyl Siding Installed
With the plumbing, electric and HVAC inspection passed, vinyl siding was completed by June 28th.